#include <GovSteam1.h>
Steam turbine governor model, based on the GovSteamIEEE1 model (with optional deadband and nonlinear valve gain added).
IEC61970::Base::Domain::Frequency IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::db1 |
Intentional deadband width (db1). Unit = Hz. Typical Value = 0.
IEC61970::Base::Domain::ActivePower IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::db2 |
Unintentional deadband (db2). Unit = MW. Typical Value = 0.
IEC61970::Base::Domain::Frequency IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::eps |
Intentional db hysteresis (eps). Unit = Hz. Typical Value = 0.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::gv1 |
Nonlinear gain valve position point 1 (GV1). Typical Value = 0.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::gv2 |
Nonlinear gain valve position point 2 (GV2). Typical Value = 0.4.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::gv3 |
Nonlinear gain valve position point 3 (GV3). Typical Value = 0.5.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::gv4 |
Nonlinear gain valve position point 4 (GV4). Typical Value = 0.6.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::gv5 |
Nonlinear gain valve position point 5 (GV5). Typical Value = 1.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::gv6 |
Nonlinear gain valve position point 6 (GV6). Typical Value = 0.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k |
Governor gain (reciprocal of droop) (K) (>0). Typical Value = 25.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k1 |
Fraction of HP shaft power after first boiler pass (K1). Typical Value = 0.2.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k2 |
Fraction of LP shaft power after first boiler pass (K2). Typical Value = 0.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k3 |
Fraction of HP shaft power after second boiler pass (K3). Typical Value = 0.3.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k4 |
Fraction of LP shaft power after second boiler pass (K4). Typical Value = 0.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k5 |
Fraction of HP shaft power after third boiler pass (K5). Typical Value = 0.5.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k6 |
Fraction of LP shaft power after third boiler pass (K6). Typical Value = 0.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k7 |
Fraction of HP shaft power after fourth boiler pass (K7). Typical Value = 0.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::k8 |
Fraction of LP shaft power after fourth boiler pass (K8). Typical Value = 0.
IEC61970::Base::Domain::ActivePower IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::mwbase |
Base for power values (MWbase) (>0). Unit = MW.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pgv1 |
Nonlinear gain power value point 1 (Pgv1). Typical Value = 0.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pgv2 |
Nonlinear gain power value point 2 (Pgv2). Typical Value = 0.75.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pgv3 |
Nonlinear gain power value point 3 (Pgv3). Typical Value = 0.91.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pgv4 |
Nonlinear gain power value point 4 (Pgv4). Typical Value = 0.98.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pgv5 |
Nonlinear gain power value point 5 (Pgv5). Typical Value = 1.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pgv6 |
Nonlinear gain power value point 6 (Pgv6). Typical Value = 0.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pmax |
Maximum valve opening (Pmax) (> Pmin). Typical Value = 1.
IEC61970::Base::Domain::PU IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::pmin |
Minimum valve opening (Pmin) (>=0). Typical Value = 0.
IEC61970::Base::Domain::Boolean IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::sdb1 |
Intentional deadband indicator. true = intentional deadband is applied false = intentional deadband is not applied. Typical Value = true.
IEC61970::Base::Domain::Boolean IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::sdb2 |
Unintentional deadband location. true = intentional deadband is applied before point "A" false = intentional deadband is applied after point "A". Typical Value = true.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t1 |
Governor lag time constant (T1). Typical Value = 0.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t2 |
Governor lead time constant (T2). Typical Value = 0.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t3 |
Valve positioner time constant (T3) (>0). Typical Value = 0.1.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t4 |
Inlet piping/steam bowl time constant (T4). Typical Value = 0.3.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t5 |
Time constant of second boiler pass (T5). Typical Value = 5.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t6 |
Time constant of third boiler pass (T6). Typical Value = 0.5.
IEC61970::Base::Domain::Seconds IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::t7 |
Time constant of fourth boiler pass (T7). Typical Value = 0.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::uc |
Maximum valve closing velocity (Uc) (<0). Unit = PU/sec. Typical Value = -10.
IEC61970::Base::Domain::Float IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::uo |
Maximum valve opening velocity (Uo) (>0). Unit = PU/sec. Typical Value = 1.
IEC61970::Base::Domain::Boolean IEC61970::Dynamics::StandardModels::TurbineGovernorDynamics::GovSteam1::valve |
Nonlinear valve characteristic. true = nonlinear valve characteristic is used false = nonlinear valve characteristic is not used. Typical Value = true.